Aegis Station
The hub/ring boundary is the interface between Aegis Station's despun central hub and its three co-rotating habitat rings. Everything the station needs to move — crew, cargo, water, power, data, heat — crosses it. The principle is singular: no continuous rotary mechanical interface carries a life-critical flow. No slip rings. No continuous rotary seals. Every crossing is contactless, cyclic, or removed by giving each side its own copy of the function.
This page is the crossing read as a mechanism, then built as flight software and run. The mechanism is a drum that is locked to the hub, locked to the ring, or being driven between them, and never free. The software is a seven-application flight computer image, a physics simulator of the drum, its locks, its berths and its bearings, and an operator console; the image has crossed hub to ring, run every fault in its library, and recorded each run.
Continuous rotary mechanical interfaces — slip rings, brush assemblies, rotary fluid unions — are the historically failure-prone elements of rotating space systems: wear, contamination, seal degradation, single points of failure. Aegis Station does not have them at the hub/ring boundary. Each flow is handled by the mechanism matched to its duty cycle:
The hub is an interface, not an umbilical. A ring with every crossing out of service stays habitable on its own power, life support and radiators. The crossing is sized for traffic: each ring is its own refuge, sectored, and is not evacuated through the hub.
At each ring face a despun spine core, 7 m across, passes through the ring collar's 8 m main bearing. On the core, between the hub bulkhead and the collar face, rides an annular magazine drum, 24 m across and 8 m long. Four through-berths at 9 m radius hold pods, 3.5 m by 7 m with a hatch at each end. The hub bulkhead has four ports; the collar face has four vestibules; the berths match both. A hub lock and a ring lock make the drum's frame explicit; a drive on the collar carries it between them; a brake on the drum's bearing stops it without the drive; a 1.1 m axial stroke pushes a pod out of its berth to mate with a port or a vestibule. Every interface is a bearing or a lock, and none of them is a seal.
| Figure | Value | Note |
|---|---|---|
| Station | ring centreline 350 m, floor 397 m, 1 g at the floor at 1.50 rpm | the hub 20 m across, the spine core 7 m through an 8 m bearing |
| Magazine drum | 24 m across, 8 m bore, 8 m long | an annulus on the despun spine core between the hub bulkhead and the ring collar face |
| Berths | four, at 9 m radius, 90° apart | matching the four hub ports and the four vestibules |
| Pod | 3.5 m × 7 m, a hatch at each end, about 8 t | 4 crew nominal, 6 in contingency; a loaded cargo pod about 53 t |
| Push stroke | 1.1 m each way at 20 mm/s | soft capture at 1.0 m, hard mate with a static seal, equalization, a 60 s leak check |
| Lock tolerance | 10 mm at the berth radius, 0.01 rpm | engagement fails safe outside it; a release under torque faults the lock |
| Spin-up | 120 s at about 10 kN·m | passenger drum, about 1.5 kW peak; the cargo drum about 14 kN·m |
| Gravity in a pod at ring rate | about 0.02 g | floor outward |
| One-way cycle | about 7.5 min for the mechanism | seal, retract, spin, lock, push, mate, as run in simulation; boarding and disembarking are the crew's time on top |
| Throughput per ring face | 64 crew/h nominal, about 144 in surge | sized for scheduled traffic; the ring is its own refuge |
An outbound crossing: boarding with the drum locked to the hub and the pods mated to the bulkhead ports; seal, hatches closed and pods pressurized; retract the pods into the drum; spin, releasing the hub lock, ramping to ring rate, closing the residual angle to the vestibules and engaging the ring lock; push the pods to the vestibules; mate, equalize and leak-check; disembark at the ring. The return is the same with the frames exchanged. The scene below is the phase model of the concept, the ring at its true rate, scrubbable to any second; the simulation's own timings are in the next section.
The crossing was built as flight software on NASA's core Flight System, on the pattern Aegis Station uses for its vehicles: seven applications (the executive that runs the cycle and refuses what the rules forbid; the drive loop with its two locks; the four berths; and monitors for the main bearing's despin, the drum's balance, the rotary transformer and the optical link) beside the stock fault-response applications, against a physics simulator of the drum, the locks, the strokes, the pressures, the bearings, the transformer and the heads, in lockstep with the flight computer's clock. The image was then run through the fault library its requirements review asks for, each run judged on the flight computer's own record: the executive's phase and its reasons, the Limit Checker's actionpoints and the stored command sequences they start.
On the flight computer image, from the operator's second command with the hatches closed to the pods ready at the ring: seal 5 s, retract 56 s, spin 164 s (release 2, ramp 111, align 49, engage 2), lock and push 59 s, mate with equalization and leak check 152 s — 436 s in all, 441 to 455 s across the later runs as the schedule falls, no fault, no refusal, the hub at zero rate throughout. Boarding, the pods docking at the hub ports and leak-checking, takes 210 s before that. The mechanism's time is about seven and a half minutes each way; the crew's boarding and disembarking are not timed by the executive. Two thirds of the spin is the ramp; the rest is closing the residual angle the ramp leaves, which is where a faster cycle would come from.
| Fault | Injected | What the flight computer did |
|---|---|---|
| Drive stall below half rate | drive torque lost 40 s into the ramp, 34 % of ring rate | the drive's own stall rule faulted within 1 s; the executive aborted and braked; the Limit Checker ran its brake sequence; the drum stopped between frames in 15 s; restored and resumed, home at the hub |
| Drive stall above half rate | the same at 90 s, 75 % | the same chain; the brake took 31 s from 1.1 rpm; home at the hub, because the brake acts toward the hub by construction and there is no way to the ring without the drive |
| Operator abort below half rate | ABORT 20 s into the ramp | the drive turned back; locked to the hub in 83 s |
| Operator abort above half rate | the stored abort sequence started from the ground 100 s into the ramp | the drive finished to the ring; locked to the ring in 71 s |
| A lock that will not release | the hub lock stuck engaged before the crossing | the mechanism refused the release and faulted the lock; the drive reported a lock fault with no torque commanded; the executive aborted on a drum that never moved; freed and cleared, idle at the hub |
| A lock that misses | the drum's angle forced 20 mm off while the ring lock's dogs seat | the engagement failed safe, the drive re-indexed and engaged on the retry; the crossing completed with no fault and no trip |
| A push without the lock | a pod pushed toward the ring with only the hub locked, bypassing the executive | the probe met the moving port, the stroke halted at 1.0 m on the capture miss, the berth faulted, the executive held, the Limit Checker ran its hold sequence; cleared and retracted, idle |
| A leak on the mate | a 0.1 kPa/s seal leak after hard mate at the ring | the leak was judged during equalization within a tick; the executive held with the hatches kept shut; fixed, cleared, the crossing completed |
| A hatch out of sequence | a hatch tried before equalization; a hatch opened during the leak check | the first was refused by the mechanism; the second was flagged in 0.3 s, the executive held, the Limit Checker tripped in 1.3 s; closed and cleared, boarding completed |
| Imbalance over limit | one 53 t cargo pod alone with three 8 t pods | the executive sized the ramp to the load cells; the balance monitor flagged the imbalance and pumped the ballast to its limit; the crossing completed in 455 s |
| Transformer gap drift | the rotary transformer's gap to 12.5 mm during the spin | the unit shut down and the power monitor said so; the Limit Checker raised an event and started nothing, because the ring is on its own power; the crossing completed; a reset at 5 mm cleared it |
| An optical head out | one of the four ring-side heads faulted during the spin | the link dropped once a revolution for the gap the head left, 89 s of outage over 62 handoffs with none over 60 s, the RF backup up; no hold; the crossing completed |
| Hub despin lost | the hub's despin drive lost 20 s into the ramp | the hub reached 0.01 rpm in 16 s and the bearing monitor flagged it; the Limit Checker held the crossing with the drive holding rate between frames; restored, the hub was despun in 7 s; resumed, the crossing completed |
What the full stack found that unit tests could not. Every one of these responses had been shown in the standalone tests first. The image found two things more. The executive accepted a HOLD during an abort, and the Limit Checker's drive-fault rule sent one the moment the executive left the spin phase to abort: the hold suspended the abort and the way to resume it was lost. The executive now refuses a hold during an abort, resumes an abort from such a hold, and the Limit Checker's rule excludes the abort. And two rows of the review's expected-outcome table were wrong: a stall above half rate cannot finish to the ring, because the brake is toward the hub; and a lock that will not release is a drive fault and an abort, not a hold. The table was corrected to what the mechanism does.
Cargo crosses in the same pod form factor as crew, on a mirror-image cargo drum at each ring face. Bulk water, pressurant gas and other fluids cross as sealed cartridges, not as flowing streams through rotating plumbing, so there is no continuous rotary fluid union anywhere on the station.
Power crosses by contactless inductive coupling: a rotary transformer at the main bearing whose primary and secondary turn against each other across a gap of a few millimetres. No brushes, no sliding contact, no wear item on the power path.
Data crosses by free-space optical links at the main bearing, close to the spin axis. The spine core passes through the bearing, so nothing on the ring side can sit on the axis itself; four ring-side heads around the bearing, with fields of ±50° that overlap, hand off to the hub-side receiver as the ring turns. No mechanical rotation of the link is required, and the link was run with a head out: it dropped once a revolution for the gap the head left and never for long enough to matter.
Most of the station's waste heat does not cross the boundary. Ring heat is rejected by ring-mounted radiators on the rotating structure, hub heat by hub-mounted radiators, which removes what would otherwise be the highest-duty-cycle wear item on the station: a continuous rotary fluid coupling on a working thermal loop.
| Flow | Crossing | Continuous rotary seal? |
|---|---|---|
| Crew | Pods on a drum locked to one frame or the other and driven between them | No |
| Cargo | The same, on the cargo drum | No |
| Bulk water | Sealed cartridges carried as cargo pod payload | No |
| Pressurant gas | Sealed gas cartridges carried as cargo pod payload | No |
| Power | Rotary transformer, contactless inductive | No |
| Data | Near-axis free-space optical with handoff | No |
| Thermal | Rejected on each side independently | No |
What exists. A requirements review of the crossing with its budgets, trades and hazards; the flight software, its simulator and its console, complete through a nominal crossing, the fault library above and a recorded, played-back run; and the drawings on this page. The requirements review is at its first baseline on these results.
What is a model. Everything. No part of the crossing has been built. The drum's mass, the bearing friction, the lock's seating time, the tunnel's equalization and the transformer's efficiency are placeholders chosen to be plausible and marked as such; the analyses that replace them (the lock's seating dynamics, the brake's sizing, an 8 m bearing in vacuum, the drum's structure) are the next work. What the simulation demonstrates is the sequence and its interlocks: that the rules of the mechanism, kept twice over by the executive and by the mechanism itself, do what the review says they do, and that every fault in the library ends somewhere safe.
Partnership. The crossing's flight software, its simulator, the console and the recorded runs are complete and are proprietary to Aegis Station. They are not slated for public release. The work is open to partnership: Aegis Station shares the code for evaluation with qualified organizations under agreement. The station's other rotating-boundary systems — the ring's balance, the cartridge berthing on the cargo drum's far side, the shield fill — follow the same path.
This page describes the boundary only. Ring-internal architecture, hub infrastructure and the overall station design are addressed elsewhere in the program documentation.
← Back to Home